Project: VRS Upgrade in Morar
Location: Mallaig, Loch Morar
Installation & Completion: September 22
Main Contractor: Highland Council
Type of work: VRS Upgrade
Project Summary:
HFBC were awarded the contract for the upgrading of barrier to comply with current standards
HFBC works:
To supply and install the following:
- 11.2m of varioguard on concrete strip
- 1 no. connection from varioguard to flexbeam
- 8m N2W2 flexbeam
- 140m N2W3 flexbeam
- 1 no. P4 terminal
The flexbeam and P4 terminal were installed concrete in with sockets.