Project: VRS Barrier upgrade A95 Meikle Cantlay
Location: A95, Near Davoch of Grange
Main Contractor: Taziker
Type of work: VRS Barrier
Project Summary:
HFBC was awarded this project and was a subcontractor on this site, with Moray Council being the employer of the contract.
The existing barrier was damaged due to erosion from the River Isla and a new vehicle restraint system was installed.
Start of project: 13th November 2023
End of project: 17th November 2023
HFBC works:
To supply and install approximately 120m of N2W2 SPR4 1 single sided VRS which includes:
- All posts and fittings for a socketed concrete-in system, with radius beams for curve.
- 1 number P4 TREND terminal.
- 1 full height anchor.
- Removal of existing VRS and terminals to ground level.
Prior to installation, the ground was scanned and a trial pitch was dug to locate services. This project was completed with no damage to existing services.