Project: Sittenham Bends Barrier

Location: Dalnavie, near Ardross Primary School

Main Contractor:​ HFBC

Type of work: Removal and installation of Road Restraint Systems – Barrier

Project Summary:

HFBC and Highland Council continue to complete successful projects together. This particular project involved replacing a section of barrier that had suffered several vehicle strikes.

Start of project: 18th March 2024

End of project: 20th March 2024

HFBC works:

Project works included the following:

  • HFBC set up a 2-way TM with lights and full signage.
  • Take down existing barrier to ground level and supply and install new N2W2 barrier with posts installed into sockets in concrete log.
  • Install 2 P4 terminals.