Project: Scottish Borders Council P4 Terminal Installation for A7
Location: A7 between Galashiels and Scottish Borders Boundary
Main Contractor: HFBC Ltd
Type of work: P4 terminal installation
Project Summary:
HFBC were contracted by Scottish Borders Council, to supply and install new P4 terminals over a 20 mile stretch of the A7.
Start of project: 10th March 2025
End of project: 28th March 2025
HFBC works:
HFBC were contracted to carry out the following:
- Take down existing terminals to ground level
- Supply, install and concrete in P4 terminals, including any tie in required to existing systems
- Carry out all traffic management for the works