Project: Scottish Borders Council P4 Terminal Installation for A7

Location: A7 between Galashiels and Scottish Borders Boundary

Main Contractor:​ HFBC Ltd

Type of work: P4 terminal installation

Project Summary:

HFBC were contracted by Scottish Borders Council, to supply and install new P4 terminals over a 20 mile stretch of the A7.

Start of project: 10th March 2025

End of project: 28th March 2025

HFBC works:

HFBC were contracted to carry out the following:

  • Take down existing terminals to ground level
  • Supply, install and concrete in P4 terminals, including any tie in required to existing systems
  • Carry out all traffic management for the works