Project: Kinlochbervie Barriers

Location: Inshegra, Lairg

Main Contractor:​ HFBC

Type of work: Repair and Renew of Road Restraint Systems – Barrier

Project Summary:

HFBC and Highland Council have completed several successful projects together. This project included repairing existing barrier that had been damaged, as well as renewing barrier that had expired its life.

Start of project: 31st October 2023

End of project: 7th November 2023

HFBC works:

Project works included the following:

  • Take down existing barrier, grade the ground level, supply and install N2W3 flexbeam SPR4 in individual socketed concrete foundations.
  • Supply and install P4 terminal.
  • Additional site area required taking down and replacing UCB posts.