Project: Inverurie Community Campus Civils & Landscaping

Location: Inverurie

Main Contractor: Robertson Construction Group

Type of work: Civils and landscaping

Project Summary:

Robertson Construction were appointed as Main Contractor for one of the largest school construction projects in Scotland. This £55 million project will now provide modern secondary education, sports and community facilities for the Inverurie area.

HFBC were awarded the sub-contract for the ground works including annual seasonal maintenance.

HFBC works:

To carry out the following:

  • De-stone, level to contours, grass seed and fertilise approx. 14,000m2
  • Supply and plant over 1000 shrubs of 10 different varieties
  • Supply and plant over 3700 trees of 22 different varieties

Start of project: June 2022

End of project: July 2022