Project: Denny Vehicle Restraint System and Pedestrian Guardrail​

Location: Denny Eastern Access Road, John Taylors Farm yard (Cuthelton Farm)

Main Contractor:​ RJ McLeod​

Type of work: Vehicle Restraint System (Barrier) and Pedestrian Guardrail

Project Summary:

HFBC was awarded this project following successful works with RJ McLeod at the M9 Winchburgh Roundabout.
This particular project was completed in two stages, with the standard driven barrier being installed first, followed by the pedestrian guardrail.

Start of project: 13th March 2024

End of project: 26th April 2024

HFBC works:

To supply and install the following:

Location 1

  • SS N2W2 SPR4 – Standard Driven
  • P4 driven trend terminals and P2 driven trend terminal

Location 2

  • Pedestrian Guardrail

Click here for more information on the Denny Eastern Access Road: https://dennyeasternaccessroad.co.uk/