Project: Craibstone Site Barrier Bucksburn
Location: Bucksburn, Aberdeen
Main Contractor: JKR Contractors
Type of work: Barrier
Project Summary:
The supply and installation of the following:
- Rondino N2W2 wood and steel restraint system
- Supply and install P1 terminals to suit
- Supply and install 90-degree bends (off road system)
Start of project: October 2023
End of project: October 2023
HFBC works:
JKR Contractors were awarded the civil engineering works. HFBC was offered to tender for 140 metres of barrier to be installed.
This was the first project completed for JKR. HFBC continues to work with JKR to install barrier and fencing systems.