Project: Broadford Cemetery Groundworks
Location: Broadford, Skye
Main Contractor: HFBC
Type of work: Plinth and Pavement Installation
Project Summary:
- Install approximately 58m of 900mm plinth.
- Install approximately 27m of unbound pavement type 1.
- Install approximately 58m of unbound pavement type 2.
- Install 2 new car parks.
- Includes for material supply and removal of arisings.
Start of project: August 2023
End of project: October 2023
HFBC works:
T Piece Sections & Paths
- Scans are completed to ensure all services are located.
- Excavator used to achieve 370mm depth.
- Excess spoil removed from the area and moved in dumper to another area of the cemetery.
- Subbase installed and compacted.
Concrete Head Stones
- Excavator used to scrape the ground, which is then lined and levelled.
- Some areas are excavated to 900mm depth.
- Shuttering installed and re-bar installed.
- Concrete poured, pokered and floated to level.