Project: A91 Stirling Barrier Repair​

Location: Skeoch Roundabout, Stirling

Main Contractor:​ HFBC​

Type of work: Barrier Repair and Installation

Project Summary:

This project was awarded to HFBC by Stirling Council. HFBC were the principal contractors on site, therefore completed all scanning of the ground and issuing of permits. This project was completed with Alba Traffic Management who delivered, set up and removed various lane closures.

Start of project: 20th March 2024

End of project: 25th March 2024

HFBC works:

Project works included:

  • Taking down the damaged barrier
  • Installing strip footing with sockets for posts
  • Reinstalling/repairing barrier

In total, 3 sections of damaged guardrail were repaired for Stirling Council.