Project: Naver Bridge Site Clearance & Vehicle Restraint System Installation

Location: Naver Bridge, A836

Main Contractor:​Wills Bros

Type of work: Site Clearance & Vehicle Restraint System Installation

Project Summary:

Wills Bros and the Highland Council collaborated on the Naver Bridge Replacement Scheme.

As part of the North Coast 500 tourist route, the bridge replacement was essential for a safer crossing over the river.

Start of project: 12 January 2026

End of project: 13 August 2026

HFBC works:

HFBC carried out site clearance, removing and chipping gorse in 2024 before returning in January 2026 to supply and install the following:

  • N2W2 VGSN 1002 parapet with mesh including connections to concrete wall
  • N2W4 barrier on driven posts
  • N2W3 barrier on driven posts
  • N2W2 barrier on driven posts
  • single sided P4 Trend Terminals driven
  • single sided P2 Trend Terminals driven
  • Tranzflex connection from N2 barrier to N2 steel parapet
  • Guardrails