Project: Balmenach Distillery Groundworks and Surfacing
Location: Cromdale, Grantown-on-Spey
Main Contractor: HFBC Ltd
Type of work: Groundworks / Surfacing
Project Summary:
To install drainage and resurface area
Start of project: 24th June 2024
End of project: 3rd July 2024
HFBC works:
Balmenach Distillery contracted HFBC Ltd to supply and install: –
- ACO drains to tie into existing manhole
- Remove tar and level out subbase
- Lay AC60mm and HRA 40mm tar layer