Project: Spey Viaduct Palisade and Rail Fencing
Location: Spey Viaduct, Garmouth
Main Contractor: HFBC Ltd
Type of work: Fencing – Palisade and Rail
Project Summary:
Spey Viaduct partially collapsed on the 15th December 2025.
Spey Viaduct is a former railway bridge which spans the mouth of the River Spey. The line opened in 1886, closed to railway traffic in 1968, and has been used as a cycle and footpath since rail closure. Click here for Garmouth/Spey Viaduct update: https://newsroom.moray.gov.uk/news/garmouthspey-viaduct-update-15-december-2025
Start of project: 17th December 2025
End of project: 18th December 2025
HFBC works:
Moray Council contracted HFBC Ltd to supply and install fencing to prevent public entry to the viaduct.
Supply and install: –
- 3 rail fencing over 2 locations, across each end of the footpath and extending either side.
- Palisade fence with dug and set footings at each end of the bridge, installed between the bridge parapet walls.