Project: Viewmill Bridge Parapet & VRS Installation
Location: Mosstowie, Moray
Main Contractor: HFBC Ltd
Type of work: Parapet & VRS Installation
Project Summary:
Moray Council contracted Aberdeen Marine Ltd to replace Viewmill Bridge, which had been damaged due to road traffic collisions.
Start of project: 23rd June 2025
End of project: 1st July 2025
HFBC works:
Aberdeen Marine Ltd contracted HFBC to remove the current parapet system.
Supply and install: –
- N2W2 VGSN 1003 without mesh
- 4 x tranzflex connection from parapet to barrier
- N2W2 SPR4 barrier
- P4 Trend terminals
HFBC carried out 2-way traffic management.