Project: Vehicle Restraint Systems Renewal for Highland Council Sites
Location: Lochaber, Badenoch and Strathspey Areas
Main Contractor: HFBC
Type of work: Vehicle Restraint Systems Renewal
Project Summary:
Highland Council contracted HFBC to carry out a full upgrade of the VRS Systems over 14 different locations over the Lochaber, Badenoch and Strathspey Areas.
Start of project: 19th May 2025
End of project: 18th June 2025
HFBC works:
HFBC removed the existing systems and carried out 14 full new installations. The VRS is installed in socketed concrete strip foundations with a containment of N2W1 and P4 SafeEnd Terminals.
HFBC carried out the 2 way Traffic Management but for the 3 way TM works Alba TM was subcontracted in.