Project: Mosstowie Primary Chainlink Fencing

Location: Milton Brae, Elgin

Main Contractor:​ HFBC

Type of work: Chainlink Fencing

Project Summary:

This project was awarded to HFBC by McLaughlin and Harvey. The fencing work was on a strict timeline, as this needed to be completed while the school was closed over the holidays.

Start of project: 8th April 2024

End of project: 10th April 2024

HFBC works:

To supply and install the following:

  • Green chainlink fence with RSA galvanised posts at 3m centres.
  • Corner strainers, end strainers and a single gate.

The HFBC site team met with a client representative on-site prior to starting the project. The work was completed on-time and within budget.