Project: VRS Barrier upgrade Lecht Brae, Strathdon, Aberdeen

Location: Lecht Brae, Strathdon, Aberdeen

Main Contractor:​ Moray Council

Type of work: VRS Barrier

Project Summary:

Upon completion of many successful projects together, HFBC was selected to quote for this project. This included replacing an expired barrier and carrying out repairs to UCB barrier at the same location.

Start of project:11th September 2023

End of project: 14th September 2023

HFBC works:

Project works included the following:

  • Traffic management is marked, laid out and erected.
  • Traffic management taken down at night and erected every morning.
  • Existing barrier to be removed.
  • Supply and install 236 metres of concrete in N2W2.