Project: Upper Achintore Fencing

Location: Ross Place Pitch, Fort William

Main Contractor:​ TSL Contractors

Type of work: Fencing

Project Summary:

TSL invited HFBC to price for the upgrading of an existing sports pitch. Prior to commencing work, HFBC completed the TSL approved subcontractor process.

This project was completed within 5 days, and HFBC looks forward to working with TSL on future projects.

Start of project: 6th November 2023

End of project: 10th November 2023

HFBC works:

Supply and install the following:

  • 108 metres of double wire panel system (2m high complete with rebound to 1.2 metre & 60×40 RHS posts at 2.520m centres complete with full length clamp bar)
  • 2m rebound goal recess 4.8m x1.2m
  • Basketball post, back board and hoop
  • 1 single leaf gate and 1 double leaf gate
  • 30m of timber post and 5 wire