Project: Branshogle Bridge Barrier
Location: Balfron near Stirling
Main Contractor: Stirling Council
Type of work: Barrier
Project Summary:
Branshogle Bridge was closed in March 2021 after partially collapsing during a period of heavy rainfall. Extensive repairs to the bridge included construction of the concrete deck, bridge deck backfilling, road widening and re-surfacing, and safety barrier installation.
Stirling Council awarded HFBC the barrier package.
Start of project: January 2023
End of project: January 2023
HFBC works:
The installation of the following:
- 4 no. single sided N2 non connection transitions in concrete foundations
- 60m N2W2 single sided flexbeam in concrete foundations
- 60m N2W1 single sided flexbeam in concrete foundations
- 1 no. P2 Trend single sided terminal in concrete foundations
- 3 no. P4 Trend single sided terminals in concrete foundations